Tuesday, 15 March 2022

PROJECT POTHOLE - COUNCIL SET TO REPAIR 'DEEP DEFECTS' ON AREA'S CARRIAGEWAYS

                                               

Defective road surfacing is a menace for road users and especially dangerous to cyclists 

A THREE-week patchwork programme for streets in North East Lincolnshire is due to start next Monday.

These works are deemed "essential to repair deep carriageway defects and ensure the road surface is fully prepared for the annual carriageway treatment programme which will take place later in the year". 

The works will take place on a rolling programme  and will involve a number of daytime road closures. 

These road closures will be in place between 7:30am and 6pm at the following locations:


Grimsby

Cooks Lane – Monday 21 March

Great Coates Road (temporary traffic lights) – Wednesday 23March


Immingham

Woodlands Avenue – Monday 28 March

Clyfton Crescent – Thursday 7 April


Cleethorpes

Belvoir Road – localised traffic management (using give and take) – Tuesday 22 March

Brampton Way – localised traffic management (using give and take) – Tuesday 22 March

Glebe Road – Tuesday 22 March

Parker Street – Thursday 24 March

Highgate – Thursday 24 March

George Street – Friday 25 March

Hey Street – Friday 25 March

Barkhouse Lane – Friday 25 March

Sherburn Street – Monday 28 March

Humber Street – Tuesday 29 March

Oole Road – Tuesday 29 March

Crow Hill Avenue – Wednesday 30 March

Whites Road – Wednesday 30 March

West Street – Thursday 31 March

Thrunscoe Road – Thursday 31 March

Reynolds Street – Tuesday 5 April

William Street – Wednesday 6 April

Bark Street – Wednesday 6 April

Albert Road – Wednesday 6 April


Stallingborough

North Moss Lane – Thursday 7 April


The above dates may be subject to change as the works are weather-dependent.

During the works, on-street parking will be temporarily suspended and residents are asked to not park vehicles on the carriageway or footpath to ensure a safe working area.

This will ensure the surface dressing treatment taking place later in the year will effectively extend the life of the carriageway. 

Further details of these works will be announced once confirmed closer to the start date.