THE ongoing revamp of Cleethorpes Market Place has fallen behind schedule.
The works began in May this year and were due to be completed in January next year, but it has emerged that will not now be the case.
According to North East Lincolnshire Council, the delay is the result of:
* Material challenges (in other words, paving materials were ordered late)
and:
* Additional work being required to the highway sub-base and drainage system
The contractors are CR Reynolds - the firm responsible for the project to resurface Grimsby's Freshney Place.
NELC's Reform UK leadership is not happy with the delays both on this and other projects - notably the renovation of Grimsby's Corporation Road bridge.
Says portfolio holder for housing, infrastructure and transport Cllr Paul Batson: "We will keep pushing and make sure this project continues at pace."
After the next few weeks, the contractors will close down for the festive holiday
Then, in the New Year, work will continue to:
* Finish off the new paving to all areas
* Carry out the works to the roads
* Install new lighting and street furniture.
* Introduce hard and soft landscaping
Subject to no further "material challenges" or other hitches, such as cold weather, it is intended that the £4.92-million project should be completed by mid-March.
According to a council official, this will then be "a fantastic public space for people to enjoy all year round".