Tuesday, 1 April 2025

Council issues start-of-the month update on long-running repairs to Grimsby's Corporation Road Bridge

                                                          


North East Lincolnshire Council has today issued this update on the Corporation Road Bridge re[pairs project.

Works to Grade II listed structure, Corporation Road Bridge have been progressing, with grit blasting and painting works continuing to Spans 5 and 6.

The northern footway has been waterproofed and is about to be surfaced to allow the switching of works to the opposite side. 

As this work is undertaken, the pedestrian footway will switch from the south side of the bridge to the north side.

A final footway treatment will be added later in the works.

To take advantage of anticipated low tide levels, weekend working will also continue to take place this month.

Footway closures are also required while works are taking place adjacent to public areas to ensure the safety of both the public and the workers on site.

To help complete remaining sections of the works the footway may be closed for  one or two days a week if conditions allow.

Footway closures will take place between 9am and 4pm each weekday as detailed below. 

The footway will remain open during the weekend working dates. Temporary signs will be in place for the footway closures.

April 2025 weekend working and footway closure dates:

South footway closures

Tuesday 1 April

Wednesday 2 April (provisional)

Wednesday 9 April

Wednesday 16 April

Wednesday 23 April

Wednesday 30 April

Weekend working

Saturday 5 April and Sunday 6 April

Saturday 19 April and Sunday 20 April

North East Lincolnshire Council, its delivery partner, Equans, and the  contractor, Spencer Group, would like to thank the public for their patience while the work is being undertaken.

No comments:

Post a Comment